The distances at a glance
| Item | Rule | 2017 NEC |
|---|---|---|
| Perimeter bonding | Extends at least 3 feet from the inside walls of the pool | 680.26(B)(2) |
| Fixed metal parts | Bonded unless more than 5 feet horizontally from the inside walls, more than 12 feet above the water, or behind a permanent barrier | 680.26(B)(7) |
| Lights, lighting outlets, ceiling fans | Over the pool or within 5 feet horizontally: generally 12 feet above maximum water level; GFCI rules for the 5-to-10-foot zone | 680.22(B) |
| Pump-motor receptacles | At least 6 feet from the inside walls | 680.22(A)(2) |
| Required general receptacle | At least one GFCI receptacle between 6 and 20 feet from the water | 680.22(A)(1) |
| Receptacles within 20 feet | 15- and 20-amp, 125-volt: GFCI protected | 680.22(A)(4) |
| Pump motors | GFCI on single-phase 120- to 240-volt pump-motor outlets, hardwired or plugged in | 680.21(C) |
| Equipment disconnect | Readily accessible, within sight, generally at least 5 feet from the inside walls | 680.13 |
| Overhead wiring | Clearances over and near the pool | 680.9 |
| Underground wiring | Location limits near the pool | 680.11 |
| Feeders to pool equipment | Feeder rules for pool panels | 680.25 |
What it means for a timber-frame pool house
- Set the posts with the pool edge on the drawing. A post within 5 feet of the inside wall pulls its steel connectors into the bonding.
- Headroom drives the fans. A low pavilion close to the water may not reach 12 feet for a ceiling fan or light. Move the fixture or move the pavilion.
- Solar racking is fixed metal. Racking or clamps within 5 feet horizontally, below 12 feet, with no barrier, generally get bonded to the pool’s equipotential bonding.
- Two systems, not one. The PV equipment ground doesn’t replace the pool bonding grid, and the bonding grid doesn’t replace the equipment ground.
- Place the disconnect early. Within sight of the pump and filter, at least 5 feet from the water, on the equipment wall before the frame is cut.
- Corrosion. Chlorine and salt air eat cheap boxes and fasteners. Stainless or coated hardware, gasketed boxes, and 680.12 and 680.14 for equipment rooms and corrosive areas.
- A vehicle charger in the pool house follows the same receptacle distances and GFCI rules.
Questions
How far from a pool must metal be bonded?
Under 2017 NEC 680.26(B)(7), fixed metal parts must be bonded unless they are more than 5 feet horizontally from the inside walls of the pool, more than 12 feet above the maximum water level, or separated by a permanent barrier. The perimeter bonding extends at least 3 feet from the inside walls.
How far must a ceiling fan or light be from a pool?
Under 2017 NEC 680.22(B), new outdoor lights, lighting outlets and ceiling-suspended fans over the pool or within 5 feet horizontally of its inside walls generally need 12 feet of clearance above the maximum water level, with specific exceptions.
How far must an outlet be from a pool?
Pool pump-motor receptacles must be at least 6 feet from the inside walls (680.22(A)(2)). Every 15- or 20-amp, 125-volt receptacle within 20 feet must be GFCI protected, and at least one GFCI receptacle is required between 6 and 20 feet from the water.
Does solar racking on a pool house need pool bonding?
If the racking or the frame's steel connectors fall within 5 feet horizontally of the inside pool wall and no exception applies, they generally get bonded to the pool's equipotential bonding. The PV equipment ground doesn't replace that bonding, and the bonding doesn't replace the equipment ground.
Where does the pool equipment disconnect go?
Under 2017 NEC 680.13: readily accessible, within sight of the equipment it serves, and generally at least 5 feet horizontally from the inside walls of the pool unless a permanent barrier separates them.
Sources
- NFPA 70, 2017 edition, Article 680.
- Connecticut DAS 2017 NEC pool, hot tub and spa checklist.
- NC Board of Examiners of Electrical Contractors (pools at one- and two-family dwellings stay on the 2017 code).
Pool notes in the field guide · Which code applies in NC
Bugging Out Solar provides the structure and the stamped structural drawings. Wire sizes, breakers, branch circuits, the point of connection and all electrical work are designed and installed by a licensed electrician under a local permit. Code notes here are pointers to check, not legal or engineering advice; your inspector has the final say.